NZTA Eastern Corridor works update

​​​​​

2020-06-11T00:00:00

11 June 2020 - NZTA Eastern Corridor works update 

The Eastern Corridor Stage 1 works are underway again and in the time since Level 3 they have re-established the construction site and got stuck into the areas they were working in prior to lockdown.
 
The Rugby Club accessway road has had its kerb & channel constructed with the road soon to be sealed. The new access road will be opened at the end of June, once it is fully complete, including new gates. As part of the project the capacity of the car park at the Clubrooms will be increased by preparing and sealing an area that is currently grass, and this will be completed over the next few weeks.

You will also see work sites along Te Ngae Road, between Sala Street and Allen Mills Road in a number of areas where they are upgrading services in partnership with Rotorua Lakes Council, such as stormwater and water mains.  The working areas will include closing the shoulder of the road at times, to ensure the crews are safely separated from road traffic.

Work will also commence soon on the northern side of Te Ngae Road, where another shared service trench will be placed from Hume Pine to Vaughan Road. This work will take approximately a month to complete, and there may be minor delays for eastbound traffic at times.

For more information and updates, please visit: www.nzta.govt.nz/projects/connect-rotorua/eastern-corridor/